Texco Drilling and Piling Ltd were contracted to install 43 concrete bored piles of both 1200mm & 900mm diameter.
Piles were drilled 24m below ground level using polymer drilling fluids to hold back the high aquifer pressures.
Leighs Cockram Joint Venture
3 months, over last quarter of 2016 (averaging
3 piles a week)
Over $1,000,000