Concrete filled bored piles

Texco Drilling and Piling Ltd were contracted to install 43 concrete bored piles of both 1200mm & 900mm diameter.

 

Piles were drilled 24m below ground level using polymer drilling fluids to hold back the high aquifer pressures.

Client

Leighs Cockram Joint Venture

Time Frame

3 months, over last quarter of 2016 (averaging

3 piles a week)

 

Contract Scale

Over $1,000,000