King Post Wall, Inland Route, Mt Lyford

Emergency works, King Post Wall

This project was conducted under the NCTIR alliance for earthquake repairs and remediation as emergency works. As such, Texco required expertise working on an active State Highway road corridor, within a strict traffic management environment.

 

These emergency works involved the construction of a 26-metre-long King Post Wall with 14 steel 310UC beam driven piles. Piles were drilled to depths of 8.2 meters, unanchored and backfilled. Timber lagging was installed by subcontracted carpenters. 

 

Works employed the Track Mounted Auger (MAIT Midi Drill) and the Track Mounted Bucket Auger (Casagrande B175XP) and operators experienced in rig operation and traffic management. 

Client

North Canterbury Transport Infrastructure Rebuild (NCTIR)

Time Frame

Sept 2017 – Feb 2018

Contact Scale

Under $500,000

“Whilst we are guided by our Safety and Quality Management Systems, we still believe in the integrity of a handshake.”